Implementation Works Schedule
10 January → 11 January 2019
Survey Set Out - Side Tree Wells
Survey set out of tree wells with intermittent disruption to parking Northbound and Southbound.
13 January 2019
Survey Set Out - Median Tree Wells
Survey set out of tree wells in the central median
14 January → 15 January 2019
Tree Well Construction - Parking Disruption to Northbound Parking along Oxford Street
Parking will be disrupted along the Northbound side of Oxford Street to accommodate construction of tree wells. Pedestrians will be able to access all businesses via footpath.
15 January → 16 January 2019
Tree Well Construction - Parking Disruption to Southbound Parking along Oxford Street
Parking will be disrupted along the Southbound side of Oxford Street to accommodate construction of tree wells. Pedestrians will be able to access all businesses via footpath.
18 January 2019
Kerb Construction - Parking Disruption to Northbound Parking along Oxford Street
Parking will be disrupted along the Northbound side of Oxford Street to accommodate kerbing of tree wells. Pedestrians will be able to access all businesses via footpath.
25 January 2019
Kerb Construction - Parking Disruption to Southbound Parking along Oxford Street
Parking will be disrupted along the Southbound side of Oxford Street to accommodate kerbing of tree wells. Pedestrians will be able to access all businesses via footpath.
03 February 2019
Sunday - Full Road Closure of Oxford Street
Full Road Closure of Oxford Street from Anzac Road to Scarborough Beach Road to create median islands and tree wells. NO VEHICLE ACCESS FROM 7AM.
09 February → 11 February 2019
Saturday, Sunday & Monday - Night Construction Works - Profile & Asphalt Oxford Street
Night Works to profile and asphalt Oxford Street (Anzac Road to Scarborough Beach Road and intersection of Scarborough Beach Road). Expect Noise - NO VEHICLE ACCESS FROM 8PM-6AM
January → February 2019
Bike Parking Consultation
Consult with businesses to determine preferred location of 12 bike racks including two love heart bike racks
January → February 2019
Monitor Oxford Street Car Park and Wilberforce Street On-Street Car Parking
Consider minor parking amendments to improve accessibility for town centre visitors
January → August 2019
30km/hr Zone Advocacy
Advocate for a reduced speed limit (30km/hr Zone) between Anzac Road and Scarborough Beach Road to Main Roads to improve safety and pedestrian and cyclist amenity
31 March 2019
Sunday - Oxford Street - Northbound Lane Closure
The northbound lane of Oxford Street and the western parking bays will be closed to traffic on Sunday 31 March. The southbound lane and eastern parking bays will remain open.
The closure is to accommodate the planting of the median island trees and median stenciling.
The closure is to accommodate the planting of the median island trees and median stenciling.